close
test_template

A Project Management Plan

download print

About this sample

About this sample

close

Words: 523 |

Page: 1|

3 min read

Published: Feb 12, 2019

Words: 523|Page: 1|3 min read

Published: Feb 12, 2019

Table of contents

  1. Project Management Plan Outline Example
  2. Introduction
    Contents of the Project Management Plan
    Development of the Project Management Plan
    Key Management Reviews
    Tools and Techniques
    Project Execution Activities
    Implementation of Corrective and Preventive Actions
  3. Project Management Plan Essay Example

Project Management Plan Outline Example

Introduction

  • Overview of project management plan and its importance in project execution
  • Mention of the integrated change control process for plan updates

Contents of the Project Management Plan

  • Explanation of the components included in the project management plan
  • Description of the purpose and significance of each component in managing a project

Development of the Project Management Plan

  • Discussion of the process of developing the project management plan
  • Emphasis on inputs, tools, and techniques used in this process

Key Management Reviews

  • Explanation of the role of key management reviews in the project management plan
  • Listing of inputs required for this step and tools and techniques used

Tools and Techniques

  • Explanation of project management methodology, project information system (PMIS), and expert judgment as tools and techniques used in the development of the plan
  • Detailed description of the PMIS components

Project Execution Activities

  • Overview of the activities required for successful project execution
  • Listing of key actions and tasks involved in project execution, including risk management, communication, data collection, and lessons learned

Implementation of Corrective and Preventive Actions

  • Explanation of how corrective actions bring project performance in line with the plan
  • Description of preventive actions to reduce potential negative consequences

Project Management Plan Essay Example

A project management plan includes all actions necessary to define, integrate, and coordinate all subsidiary and complementing plans into a cohesive project management plan. It defines how the project is executed, monitored and controlled, and closed. The project management plan is updated and revised through the integrated change control process. In addition, the process of developing project management plan documents the collection of outputs of planning processes and includes the following:

'Why Violent Video Games Shouldn't Be Banned'?

Project management processes selected by the project management team

  • Level of implementation of each selected process
  • Descriptions of tools and techniques to be used for accomplishing those processes
  • How selected processes will be used to manage the specific project
  • How work will be executed to accomplish the project objectives
  • How changes will be monitored and controlled
  • How configuration management will be performed
  • How integrity of the performance measurement baselines will be maintained and used
  • The requirements and techniques for communication among stakeholders
  • The selected project life cycle and, for multiphase projects, the associated project phases

Key management reviews for content, extent, and timing Inputs to Step 3 are the same as defined previously and include preliminary project scope statement, project management processes, enterprise environmental factors, and organizational process assets.

The tools and techniques for Step 3 are project management methodology, project information system, and expert judgment. Project management methodology defines a process that aids a project management team in developing and controlling changes to the project plan. PMIS at this step covers the following segments:

Automated system, which is used by the project team to do the following:

  • Support generation of the project management plan
  • Facilitate feedback as the document is developed
  • Control changes to the project management plan
  • Release the approved document

Configuration management system, which is a subsystem that includes sub processes for accomplishing the following:

Get a custom paper now from our expert writers.

  • Submitting proposed changes
  • Tracking systems for reviewing and authorizing changes
  • Providing a method to validate approved changes
  • Implementing change management system• Configuration management system, which forms a collection of formal procedures used to apply technical and administrative oversight to do the following:
  • Identify and document functional and physical characteristics of a product or component
  • Control any changes to such characteristics
  • Record and report each change and its implementation status
  • Support audit of the products or components to verify conformance to requirements

Change control system is the segment of PMIS that provides a collection of formal procedures that define how project deliverables and documentation are controlled. Step 4 requires the project manager and project team to perform multiple actions to execute the project plan successfully. Some of the required activities for project execution are summarized below:

  • Perform activities to accomplish project objectives
  • Expend effort and spend funds• Staff, train, and manage project team members
  • Obtain quotation, bids, offers, or proposals as appropriate
  • Implement planned methods and standards
  • Create, control, verify, and validate project deliverables
  • Manage risks and implement risk response activities
  • Manage sellers
  • Adapt approved changes into scope, plans, and environment
  • Establish and manage external and internal communication channels
  • Collect project data and report cost, schedule, technical and quality progress and status information to facilitate forecasting
  • Collect and document lessons learned and implement approved process improvement activities
  • The process of directing and managing project execution also requires implementation of the following:
  • Approved corrective actions that will bring anticipated project performance into compliance with the plan
  • Approved preventive actions to reduce the probability of potential negative consequences
Image of Prof. Linda Burke
This essay was reviewed by
Prof. Linda Burke

Cite this Essay

A Project Management Plan. (2019, February 11). GradesFixer. Retrieved April 25, 2024, from https://gradesfixer.com/free-essay-examples/a-project-management-plan/
“A Project Management Plan.” GradesFixer, 11 Feb. 2019, gradesfixer.com/free-essay-examples/a-project-management-plan/
A Project Management Plan. [online]. Available at: <https://gradesfixer.com/free-essay-examples/a-project-management-plan/> [Accessed 25 Apr. 2024].
A Project Management Plan [Internet]. GradesFixer. 2019 Feb 11 [cited 2024 Apr 25]. Available from: https://gradesfixer.com/free-essay-examples/a-project-management-plan/
copy
Keep in mind: This sample was shared by another student.
  • 450+ experts on 30 subjects ready to help
  • Custom essay delivered in as few as 3 hours
Write my essay

Still can’t find what you need?

Browse our vast selection of original essay samples, each expertly formatted and styled

close

Where do you want us to send this sample?

    By clicking “Continue”, you agree to our terms of service and privacy policy.

    close

    Be careful. This essay is not unique

    This essay was donated by a student and is likely to have been used and submitted before

    Download this Sample

    Free samples may contain mistakes and not unique parts

    close

    Sorry, we could not paraphrase this essay. Our professional writers can rewrite it and get you a unique paper.

    close

    Thanks!

    Please check your inbox.

    We can write you a custom essay that will follow your exact instructions and meet the deadlines. Let's fix your grades together!

    clock-banner-side

    Get Your
    Personalized Essay in 3 Hours or Less!

    exit-popup-close
    We can help you get a better grade and deliver your task on time!
    • Instructions Followed To The Letter
    • Deadlines Met At Every Stage
    • Unique And Plagiarism Free
    Order your paper now